In a shocking revelation, an official Government of India document accepts that an astounding 300 major and medium irrigation project costing Rs.122,060 crores, comprising 63 per cent of the major and medium irrigation projects under implementation in the country, have been going on without clearances from the Central Water Commission, the Planning Commission, the Public Investment Board or the Cabinet Committee on Economic Affairs.
The December 2006 Report of the Working Group on Water Resources for the 11th Five Year Plan chaired by Secretary, Union Ministry of Water Resources Gauri Chatterji reveals that of the 477 major and medium irrigation projects that will spill over into the 11th Plan (which was to begin on April 1, 2007, but is pending approval of the National Development Council), "around 63% of the 477 projects are unapproved; it is desirable to emphasize the concerned State Governments to take up needful steps for their early clearance." The 477 projects include 166 major, 222 medium and 89 ERM (Extension, Renovation, Modernisation) projects. Rs.41,128 crores have already been spent on these unapproved projects until March 2007. These projects are supposed to create irrigation potential of 79.47 lakh hectares.
What should happen when a project, especially one where substantial expenditure is involved, begins without the necessary approvals? The report does not call for penalties; instead it argues that once the necessary clearance is obtained, "Central Assistance/ Funding can be provided for their early implementation." Implicit in this statement is the fact that central agencies rarely disapprove a project - another serious comment on the decay in the functioning of the central water agencies. The Polavaram dam on the Godavari river in Andhra Pradesh and the building of the Hansi Butana Bhakhra Mainline Link Canal by Haryana are examples of recent times where the project work has been going on even without necessary approvals from the Central Water Commission.
Significance
The Central Water Commission, as per the latest available annual report of that organisation, is "an attached premier technical organisation of the Ministry of Water Resources" and is "responsible for overall planning and development of river basins, national perspective plan for water resources development in accordance with the National Water Policy, techno-economic appraisal of Water Resources Projects and assistance to the States in the formulation and implementation of projects, monitoring, management, design, research". This important role, however, is diluted by the fact that the current approval process at the Centre for such projects is procedural, and not statutory. The 11th Plan document states, "The complex process of investment approval of Planning Commission preceded by techno-economic clearance after examination by Central Agencies is a procedural requirement for obtaining the plan finance and not a statutory requirement. As a result, an unmanageable number of unapproved projects have been taken up by the States for implementation."
But instead of using such powers, the central agencies work more like the agents and catalysts for such sub-optimal development. The states are happy to take up projects wherever they want to, without the Centre's approval. They know that once the project is fait accompli, they can always get the central approval then, as it is unlikely to be denied once the project has begun. Some other well known problems in the functioning of the CWC include: lack of credible post facto evaluations of the projects, failure of the agency in its flood forecasting and flood management issues, failure to either assess the impact of global warming on India's water sector, failure of the agency to correctly assess the siltation of India's reservoirs and take some effective action to reduce the siltation.
A central agency like CWC is bound to fail to some degree, considering the huge task given to it, and particularly in the absence of similar institutes at the state level and further downstream. But the absence of such institutions, and absence of a culture of scientific enquiry and accountability mechanisms can also additionally be counted among the failures of CWC, and for that the blame lies only with itself.
A second, even more disturbing recommendation is this: with the central agencies having already failed in their the CWC be given even wider powers - to give statutory approvals in addition to the procedural ones it is now authorised to give. "It would, therefore, be appropriate to include investment clearance for interstate irrigation projects under Item-20 as Item-20(B) (in concurrent list of subjects in India's constitution) to give constitutional backing for Central clearance. Appraisal should necessarily be made mandatory to bring all water projects under the process of TAC/investment clearance, possibly through legislative measures in order to put hold on mushroom growth of unapproved projects, being carried through plan to plan, causing thin spreading of resources and inordinate delay in completion of projects."
Reason for hope?
However, the report isn't all bad news for the governance and administration of water. The document makes another recommendation in this regard, which is certainly welcome, "Secondly at present, detailed documentation regarding examination of alternative options to optimally meet the overall objectives and aspirations in the light of basin plan is not given in the Feasibility Report/DPR. A detailed chapter analysing the available options, even not involving large dams, should preferably be included in the DPR of future project proposals." To make this a reality, the central agencies can use the existing powers at their command.